All Items
Every RFI, change, payment, decision and deliverable, each tied to the email it came from.
Design & tender · 3
Full design and contract administration for the new wing.
Next step: Not yet recorded · Updated Sep 10 · 0 linked sources
Northstar was the lowest compliant bid at $3,480,000.
Next step: Not yet recorded · Updated Oct 28 · 0 linked sources
Contract price $3,480,000 before GST. The association holds a $150,000 contingency outside the contract.
Next step: Not yet recorded · Updated Nov 18 · 0 linked sources
Changes · 9
An old water line, not on the survey, ran through the new east footings. Executed by all three parties.
Next step: Not yet recorded · Updated Jan 22 · 0 linked sources
The association asked for conduit and boxes for a future sound system. Executed by all three parties.
Next step: Not yet recorded · Updated Feb 26 · 0 linked sources
Bedrock was higher than the geotechnical report expected. Executed by all three parties.
Next step: Not yet recorded · Updated Mar 19 · 0 linked sources
The association chose to defer the canopy to a later phase. Executed by all three parties.
Next step: Not yet recorded · Updated Apr 30 · 0 linked sources
Duct as drawn would have cut into the required gym clear height. Executed by all three parties.
Next step: Not yet recorded · Updated Jun 11 · 0 linked sources
Two more illuminated exit signs, added at framing inspection. Executed by all three parties.
Next step: Not yet recorded · Updated Jul 23 · 0 linked sources
Difference between the specified floor and a sprung system the association preferred. Executed by all three parties.
Next step: Not yet recorded · Updated Sep 10 · 0 linked sources
Required by the City's plan review comment on the link corridor. Halden recommends it; waiting on the association's approval.
Next step: Riverside Community Association · Due Oct 30 · Updated Oct 9 · 0 linked sources
Priced at the association's request. Waiting on the association to choose between the manual and motorized curtain.
Next step: Halden Architects · Due Nov 6 · Updated Oct 16 · 0 linked sources
Money · 15
Work to date $174,000; $160,950.00 due before GST. Certified by Halden.
Next step: Not yet recorded · Updated Feb 11 · 0 linked sources
Work to date $418,000; $225,700.00 due before GST. Certified by Halden.
Next step: Not yet recorded · Updated Mar 10 · 0 linked sources
Work to date $702,000; $262,700.00 due before GST. Certified by Halden.
Next step: Not yet recorded · Updated Apr 10 · 0 linked sources
Work to date $1,015,000; $289,525.00 due before GST. Certified by Halden.
Next step: Not yet recorded · Updated May 11 · 0 linked sources
Work to date $1,330,000; $291,375.00 due before GST. Certified by Halden.
Next step: Not yet recorded · Updated Jun 9 · 0 linked sources
Work to date $1,640,000; $286,750.00 due before GST. Certified by Halden.
Next step: Not yet recorded · Updated Jul 10 · 0 linked sources
Work to date $1,905,000; $245,125.00 due before GST. Certified by Halden.
Next step: Not yet recorded · Updated Aug 11 · 0 linked sources
Work to date $2,170,000; $245,125.00 due before GST. Certified by Halden.
Next step: Not yet recorded · Updated Sep 16 · 0 linked sources
Work to date $2,408,000; $220,150.00 due before GST. With Halden for certification.
Next step: Halden Architects · Updated Oct 5 · 0 linked sources
Funded pay application 4.
Next step: Not yet recorded · Updated May 28 · 0 linked sources
Funded pay application 5.
Next step: Not yet recorded · Updated Jun 25 · 0 linked sources
Funded pay application 6.
Next step: Not yet recorded · Updated Aug 8 · 0 linked sources
Funded pay application 7.
Next step: Not yet recorded · Updated Aug 27 · 0 linked sources
Funded pay application 8.
Next step: Not yet recorded · Updated Sep 24 · 0 linked sources
Waiting on an updated cost-to-complete the credit union asked for.
Next step: Riverside Community Association · Due Nov 5 · Updated Oct 15 · 0 linked sources
City & permits · 4
Issued Sep 2 after one round of plan review comments.
Next step: Not yet recorded · Updated Sep 2 · 0 linked sources
Issued to Northstar's plumbing subcontractor.
Next step: Not yet recorded · Updated Jan 14 · 0 linked sources
Issued to Brightline Electric.
Next step: Not yet recorded · Updated Feb 9 · 0 linked sources
Passed with two notes: add exit signage (now CO 6) and fire-stop two penetrations.
Next step: Not yet recorded · Updated Jul 14 · 0 linked sources
Questions & submittals · 5
Northstar asked whether the two roof drains can shift 600 mm to clear a joist. Waiting on Halden.
Next step: Halden Architects · Updated Oct 5 · 1 linked source
Answered by Halden in 4 days: 2,100 mm to the top of the pad.
Next step: Not yet recorded · Updated Oct 13 · 0 linked sources
Answered in 2 days: match the existing building's satin stainless.
Next step: Not yet recorded · Updated Oct 20 · 0 linked sources
Returned 'revise and resubmit' twice for the economizer controls. The third submission has been with Corvid since Oct 12.
Next step: Corvid Engineering · Updated Oct 12 · 1 linked source
Reviewed, no exceptions taken. Install needs the building heated to 15 °C for 7 days first.
Next step: Not yet recorded · Updated Sep 24 · 0 linked sources
Meetings & decisions · 3
Halden needs the choice to finalize the ceiling grid. Asked Oct 12; the committee meets Oct 28.
Next step: Riverside Community Association · Due Oct 30 · Updated Oct 12 · 1 linked source
Chosen at the Oct 1 site meeting: palette B.
Next step: Not yet recorded · Updated Oct 1 · 1 linked source
The floor installer needs 7 days at 15 °C. RTU-2 start-up depends on its submittal clearing review.
Next step: Northstar Construction · Due Nov 9 · Updated Oct 18 · 0 linked sources