Every meeting series, whether minutes went out and to whom, what was decided, and who took away which action. Takeaways are written by the record from the minutes. They are a summary to check, not the minutes themselves.
Open action items · 3
| Action | Who | Due | From |
|---|---|---|---|
| Answer RFI 21 (roof drains) | Mei Tanaka | Oct 10 | Site meeting 13 |
| Decide on the divider curtain | Jordan Ellis | Oct 30 | Site meeting 14 |
| Complete third review of RTU-2 | Patrick Doyle | Oct 27 | Site meeting 14 |
Site meeting · 3
No record of #1, #2, #3, #4, #5, #6, #7, #8, #9, #10, #11Site meeting 14Oct 22 · 4 attendingAgenda only · no minutes recorded
Action items
- OpenDecide on the divider curtain· Jordan Ellis · due Oct 30
- OpenComplete third review of RTU-2· Patrick Doyle · due Oct 27
Attending: Jordan Ellis (Riverside Community Association), Dana Whitford (Northstar Construction), Tom Becker (Northstar Construction), Mei Tanaka (Halden Architects)
Site meeting 13Oct 1 · 4 attendingMinutes distributed
Takeaways (written by the record; check against the minutes)
- Program room colours chosen: palette B.
- RTU-2 submittal returned a second time; start-up drives the gym floor date.
- Fire separation at the link corridor is needed per the City's plan review.
Decisions
- Finish palette B for the program rooms.
Action items
- ✓ DoneResubmit RTU-2 with revised controls· Tom Becker · due Oct 10
- ✓ DonePrice the link corridor fire separation· Dana Whitford · due Oct 9
- OpenAnswer RFI 21 (roof drains)· Mei Tanaka · due Oct 10
Still open
- Manual or motorized divider curtain?
Attending: Jordan Ellis (Riverside Community Association), Dana Whitford (Northstar Construction), Tom Becker (Northstar Construction), Mei Tanaka (Halden Architects)Sent Oct 3 to Owner, Northstar, Halden, Corvid
Site meeting 12Sep 3 · 4 attendingMinutes distributed
Takeaways (written by the record; check against the minutes)
- Roof membrane on schedule for early October.
- Sprung floor upgrade approved in principle (became CO 7).
Decisions
- Proceed with the sprung gymnasium floor.
Action items
- ✓ DonePrice the sprung floor upgrade· Dana Whitford · due Sep 8
Attending: Jordan Ellis (Riverside Community Association), Dana Whitford (Northstar Construction), Tom Becker (Northstar Construction), Mei Tanaka (Halden Architects)Sent Sep 5 to Owner, Northstar, Halden, Corvid