Change Order
COCO. Change order: a signed change. The contract amount moves. 5 · Reroute supply duct to clear the gym ceiling height
Executed$6,950.00
Duct as drawn would have cut into the required gym clear height. Executed by all three parties.
Next step: Not yet recorded · updated Jun 11
Who reviews and signs
- 1Review · Halden Architects (Mei Tanaka)Done · 06/06Signed copy received: Halden's review stamp is on the change order
- 2Sign · Riverside Community Association (Jordan Ellis)Done · 06/11Signed copy received: Signed copy received
- 3Sign · Northstar Construction (Dana Whitford)Done · 06/11Signed copy received: Signed copy received
- Every step is done. Steps with the same number can happen at the same time.
Chain
- CCN 07
- PCO 011
- CO 5
What this change order covers
The emails don't say what this change order covers, and no priced change matches its amount. Ask the contractor for the breakdown, then note it here.
History
- Jun 2 · Northstar ConstructionPCO 011 priced by Northstar
- Jun 6 · Halden ArchitectsReviewed and recommended by Halden
- Jun 11 · Riverside Community AssociationSigned by the owner and Northstar
Paper trail · 0
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
Visible to: Owner, consultants and contractor