Everything sent to riverside-wing@plumbrecord.com, plus anything forwarded or recovered. Email stays the way the team works; this is the searchable copy.
7 emails
Draw 6 – cost to completeOct 15Alex Shah · Prairie Credit Union
Jordan, before we fund Draw 6 we need an updated cost-to-complete from the contractor. The last one we have is from July. Alex
Open the whole thread →5212 RFI 21 roof drains – following upOct 14Dana Whitford · Northstar Construction
Hi Mei, following up on RFI 21. The roofer is waiting on this to finish the parapet flashing. Can we get an answer this week? Dana
Open the whole thread →HA-24-31 Divider curtain selectionOct 12Mei Tanaka · Halden ArchitectsPCO-018.pdf
Jordan, we need the association's choice between the manual and motorized divider curtain to finalize the ceiling grid. Northstar's price for the motorized option is PCO 018. Mei
Open the whole thread →HA-24-31 PCO 017 fire separationOct 12Mei Tanaka · Halden Architects
We've reviewed Northstar's price for the link corridor fire separation required by the City. It's reasonable and we recommend approval. Mei
Open the whole thread →RTU-2 resubmittalOct 12Tom Becker · Northstar ConstructionRTU-2-rev3.pdf
Third submission for RTU-2 attached with the revised controls sequence. Start-up is what drives heat for the gym floor. Tom
Open the whole thread →5212 Pay application 9Oct 5Erin Wu · Northstar ConstructionPA09.pdf, StatDec-PA9.pdf, WCB-September.pdf
Attached: pay application 9 for September, the statutory declaration and our WCB clearance letter. Erin
Open the whole thread →Site meeting 13 minutesOct 3Mei Tanaka · Halden ArchitectsSM13-minutes.pdf
Minutes of the Oct 1 site meeting attached. The committee chose finish palette B for the program rooms. Mei
Open the whole thread →