All Items
Every RFI, change, payment, decision and deliverable, each tied to the email it came from.
Changes · 2
Required by the City's plan review comment on the link corridor. Halden recommends it; waiting on the association's approval.
Next step: Riverside Community Association · Due Oct 30 · Updated Oct 9 · 0 linked sources
Priced at the association's request. Waiting on the association to choose between the manual and motorized curtain.
Next step: Halden Architects · Due Nov 6 · Updated Oct 16 · 0 linked sources
Money · 2
Work to date $2,408,000; $220,150.00 due before GST. With Halden for certification.
Next step: Halden Architects · Updated Oct 5 · 0 linked sources
Waiting on an updated cost-to-complete the credit union asked for.
Next step: Riverside Community Association · Due Nov 5 · Updated Oct 15 · 0 linked sources
Questions & submittals · 2
Northstar asked whether the two roof drains can shift 600 mm to clear a joist. Waiting on Halden.
Next step: Halden Architects · Updated Oct 5 · 1 linked source
Returned 'revise and resubmit' twice for the economizer controls. The third submission has been with Corvid since Oct 12.
Next step: Corvid Engineering · Updated Oct 12 · 1 linked source
Meetings & decisions · 2
Halden needs the choice to finalize the ceiling grid. Asked Oct 12; the committee meets Oct 28.
Next step: Riverside Community Association · Due Oct 30 · Updated Oct 12 · 1 linked source
The floor installer needs 7 days at 15 °C. RTU-2 start-up depends on its submittal clearing review.
Next step: Northstar Construction · Due Nov 9 · Updated Oct 18 · 0 linked sources