Potential change order
PCOPCO. Potential change order: the contractor's price for a change, before anyone signs it. 017 · Fire separation upgrade at the link corridor
Owner approval needed$14,300.00
Required by the City's plan review comment on the link corridor. Halden recommends it; waiting on the association's approval.
Next step: Riverside Community Association · held 15 days · due Oct 30 · updated Oct 9
Who reviews and signs
- 1Review · Halden Architects (Mei Tanaka)Done · 10/12Contract default: Typical under CCDC 2: the consultant reviews the contractor's price
- 2Approve · Riverside Community Association (Jordan Ellis)Their turnWaitingAsked for in an email: Dana asked the association to approve or decline · 90% sure
- Step 2 of 2 is next. Steps with the same number can happen at the same time.
History
- Oct 3 · Halden ArchitectsPCO 017 requested
- Oct 9 · Northstar ConstructionPriced by Northstar at $14,300
Paper trail · 0
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
Visible to: Owner, consultants and contractor