Saturday, October 24 · Construction
Share a SummaryHere's where Riverside stands.
3 things need you, 2 serious problems are open, and the next hard date is Oct 30. Nothing has gone quiet. Substantial performance is forecast for Feb 19, 3 weeks after plan.
ScheduleSlipping
Substantial performanceSubstantial performance. The point the work is essentially finished and usable. It starts the holdback and lien clocks.Forecast Feb 19Planned Jan 29 · 3 weeks after plan
Time used77%
Work billed68%
Next: Permanent heat on, Nov 9 (planned Nov 2)
All 8 milestones →Measured against the contract schedule (Schedule B, Nov 18, 2025). Latest date from Northstar schedule rev 4 (Oct 9).Coming up
- Oct 30PCO 017 · Fire separation upgrade at the link corridorNext step: You
- Oct 30Choose the gym divider curtain: manual or motorizedNext step: You
- Nov 5Draw 6 is waiting on an updated cost-to-completeNext step: Northstar Construction
- Nov 9Gym floor install needs permanent heat by Nov 9Next step: Northstar Construction
Needs attention
- PCO 017 · Fire separation upgrade at the link corridorWaiting on you · 15 daysDue Oct 30
- Choose the gym divider curtain: manual or motorizedWaiting on you · 12 daysDue Oct 30
- Draw 6 is waiting on an updated cost-to-completeSerious · Waiting on Northstar ConstructionDue Nov 5
- Gym floor install needs permanent heat by Nov 9Serious · Waiting on Northstar ConstructionDue Nov 9
Gone Quiet
Nothing has gone quiet. Every open item has had email in the last 60 days.
What happened recentlyRecently
- Oct 20 · Halden ArchitectsHalden answeredRFI 23 · Program room door hardware finish
- Oct 18 · Northstar ConstructionRFI 23 sentRFI 23 · Program room door hardware finish
- Oct 18 · Northstar ConstructionNorthstar flagged the floor install date at the site meetingAction item · Permanent heat on before the gym floor install
- Oct 16 · Northstar ConstructionPriced by Northstar at $4,600PCO 018 · Motorized gym divider curtain
- Oct 16 · Halden ArchitectsField review issuedFR 07 · Halden field review 7