Pay application
Pay app 9 · September progress billing
With Halden for certification$220,150.00
Work to date $2,408,000; $220,150.00 due before GST. With Halden for certification.
Next step: Halden Architects · held 19 days · updated Oct 5
Who reviews and signs
- 1Certify · Halden Architects (Mei Tanaka)Their turnWaitingContract default: Typical under CCDC 2 GC 5.3: the Payment Certifier certifies the amount due
- 2Approve · Riverside Community Association (Sam Okafor)WaitingContract default: The owner approves payment of the certified amount
- Step 1 of 2 is next. Steps with the same number can happen at the same time.
History
- Oct 5 · Northstar ConstructionPay application 9 submitted
Paper trail · 0
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
Visible to: Owner, consultants and contractor