Pay application
Pay app 6 · June progress billing
Certified and paid$286,750.00
Work to date $1,640,000; $286,750.00 due before GST. Certified by Halden.
Next step: Not yet recorded · updated Jul 10
Who reviews and signs
- 1Certify · Halden Architects (Mei Tanaka)Done · 07/10Signed copy received: Certificate for payment received
- 2Approve · Riverside Community Association (Sam Okafor)Done · 08/07Contract default: The owner approves payment of the certified amount
- Every step is done. Steps with the same number can happen at the same time.
History
- Jul 6 · Northstar ConstructionPay application 6 submitted
- Jul 10 · Halden ArchitectsCertificate for payment issued
Paper trail · 0
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
Visible to: Owner, consultants and contractor