Change Order
COCO. Change order: a signed change. The contract amount moves. 4 · Delete the exterior entrance canopy (credit)
Executed-$12,400.00
The association chose to defer the canopy to a later phase. Executed by all three parties.
Next step: Not yet recorded · updated Apr 30
Who reviews and signs
- 1Review · Halden Architects (Mei Tanaka)Done · 04/25Signed copy received: Halden's review stamp is on the change order
- 2Sign · Riverside Community Association (Jordan Ellis)Done · 04/30Signed copy received: Signed copy received
- 3Sign · Northstar Construction (Dana Whitford)Done · 04/30Signed copy received: Signed copy received
- Every step is done. Steps with the same number can happen at the same time.
Chain
- PCO 008
- CO 4
What this change order covers
The emails don't say what this change order covers, and no priced change matches its amount. Ask the contractor for the breakdown, then note it here.
History
- Apr 21 · Northstar ConstructionPCO 008 priced by Northstar
- Apr 25 · Halden ArchitectsReviewed and recommended by Halden
- Apr 30 · Riverside Community AssociationSigned by the owner and Northstar
Paper trail · 0
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
Visible to: Owner, consultants and contractor