Change Order
COCO. Change order: a signed change. The contract amount moves. 1 · Reroute abandoned water line found at the new footings
Executed$18,600.00
An old water line, not on the survey, ran through the new east footings. Executed by all three parties.
Next step: Not yet recorded · updated Jan 22
Who reviews and signs
- 1Review · Halden Architects (Mei Tanaka)Done · 01/17Signed copy received: Halden's review stamp is on the change order
- 2Sign · Riverside Community Association (Jordan Ellis)Done · 01/22Signed copy received: Signed copy received
- 3Sign · Northstar Construction (Dana Whitford)Done · 01/22Signed copy received: Signed copy received
- Every step is done. Steps with the same number can happen at the same time.
Chain
- CCN 02
- PCO 003
- CO 1
What this change order covers
The emails don't say what this change order covers, and no priced change matches its amount. Ask the contractor for the breakdown, then note it here.
History
- Jan 13 · Northstar ConstructionPCO 003 priced by Northstar
- Jan 17 · Halden ArchitectsReviewed and recommended by Halden
- Jan 22 · Riverside Community AssociationSigned by the owner and Northstar
Paper trail · 0
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
Visible to: Owner, consultants and contractor