Submittal
SUB-23 81 19 · Rooftop unit (RTU-2) submittalsubmittal. Product data or shop drawings the contractor sends for the design team to review before buying or building.
Third review with Corvid
Returned 'revise and resubmit' twice for the economizer controls. The third submission has been with Corvid since Oct 12.
Next step: Corvid Engineering · held 12 days · updated Oct 12
Who reviews and signs
No sign-off is recorded yet. For a submittal it usually goes like this. Confirm or change it:
- 1Review · Northstar ConstructionTheir turnWaitingContract default: Typical under CCDC 2 GC 3.10: the contractor reviews it before it goes to the consultant
- 2Review · Halden ArchitectsWaitingContract default: Typical under CCDC 2 GC 3.10: the consultant reviews for conformance with the design
- Step 1 of 2 is next. Steps with the same number can happen at the same time.
History
- Aug 28 · Northstar ConstructionFirst submission
- Sep 8 · Corvid EngineeringRevise and resubmit (controls)
- Sep 29 · Corvid EngineeringSecond revise and resubmit
- Oct 12 · Northstar ConstructionThird submission
Paper trail · 1
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
EmailOct 12Email “RTU-2 resubmittal” · Oct 12 →
Visible to: Owner, consultants and contractor