Action item
Permanent heat on before the gym floor install
Depends on RTU-2
The floor installer needs 7 days at 15 °C. RTU-2 start-up depends on its submittalsubmittal. Product data or shop drawings the contractor sends for the design team to review before buying or building. clearing review.
Next step: Northstar Construction · held 6 days · due Nov 9 · updated Oct 18
History
- Oct 18 · Northstar ConstructionNorthstar flagged the floor install date at the site meeting
Paper trail · 0
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
Visible to: Owner, consultants and contractor