Change Order
COCO. Change order: a signed change. The contract amount moves. 3 · Rock excavation at the north footings
Executed$27,400.00
Bedrock was higher than the geotechnical report expected. Executed by all three parties.
Next step: Not yet recorded · updated Mar 19
Who reviews and signs
- 1Review · Halden Architects (Mei Tanaka)Done · 03/14Signed copy received: Halden's review stamp is on the change order
- 2Sign · Riverside Community Association (Jordan Ellis)Done · 03/19Signed copy received: Signed copy received
- 3Sign · Northstar Construction (Dana Whitford)Done · 03/19Signed copy received: Signed copy received
- Every step is done. Steps with the same number can happen at the same time.
Chain
- CCN 04
- PCO 007
- CO 3
What this change order covers
The emails don't say what this change order covers, and no priced change matches its amount. Ask the contractor for the breakdown, then note it here.
History
- Mar 10 · Northstar ConstructionPCO 007 priced by Northstar
- Mar 14 · Halden ArchitectsReviewed and recommended by Halden
- Mar 19 · Riverside Community AssociationSigned by the owner and Northstar
Paper trail · 0
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
Visible to: Owner, consultants and contractor