Submittal
SUB-09 64 66 · Sprung gymnasium floor system
Reviewed
Reviewed, no exceptions taken. Install needs the building heated to 15 °C for 7 days first.
Next step: Not yet recorded · updated Sep 24
Who reviews and signs
No sign-off is recorded yet. For a submittal it usually goes like this. Confirm or change it:
- 1Review · Northstar ConstructionTheir turnWaitingContract default: Typical under CCDC 2 GC 3.10: the contractor reviews it before it goes to the consultant
- 2Review · Halden ArchitectsWaitingContract default: Typical under CCDC 2 GC 3.10: the consultant reviews for conformance with the design
- Step 1 of 2 is next. Steps with the same number can happen at the same time.
History
- Sep 17 · Northstar ConstructionSubmitted
- Sep 24 · Halden ArchitectsNo exceptions taken
Paper trail · 0
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
Visible to: Owner, consultants and contractor