RFI
RFIRFI. Request for information: a question from the builder to the design team. 22 · Gym wall padding mounting height
Answered
Answered by Halden in 4 days: 2,100 mm to the top of the pad.
Next step: Not yet recorded · updated Oct 13
Who reviews and signs
No sign-off is recorded yet. For a rfi it usually goes like this. Confirm or change it:
- 1Review · Halden ArchitectsTheir turnWaitingContract default: The consultant answers the question
- 2Acknowledge · Northstar ConstructionWaitingContract default: The contractor confirms whether the answer changes cost or time
- Step 1 of 2 is next. Steps with the same number can happen at the same time.
History
- Oct 9 · Northstar ConstructionRFI 22 sent
- Oct 13 · Halden ArchitectsHalden answered
Paper trail · 0
Every email and document this item was read from, oldest first. Each opens the project's own copy. Nothing is in the record without a source.
Visible to: Owner, consultants and contractor