Schedule
Every milestone, planned against the latest date anyone has given, with where each date came from. Read from the schedules, minutes and emails on the project; nobody keeps a separate tracker.
ScheduleSlipping
Substantial performanceSubstantial performance. The point the work is essentially finished and usable. It starts the holdback and lien clocks.Forecast Feb 19Planned Jan 29 · 3 weeks after plan
Time used77%
Work billed68%
Next: Permanent heat on, Nov 9 (planned Nov 2)
Measured against the contract schedule (Schedule B, Nov 18, 2025). Latest date from Northstar schedule rev 4 (Oct 9).Timeline · planned, revised and actual
Contract schedule (Schedule B, Nov 18, 2025) Northstar schedule rev 4 (Oct 9) What happened (from emails)
DecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMar
Site work and foundations
Structure and roof framing
Roofing and envelope
Mechanical and electrical rough-in
Permanent heat (RTU-2)
Interior finishes
Gym floor
Commissioning and closeout
MilestonesPurple line: today
Milestones · 8
- Mobilized on siteSite meeting 1 minutesDone Dec 1Planned Dec 1
- Foundations completeNorthstar schedule rev 2 (Apr 2)Done Mar 27Planned Mar 13 · 2 weeks after plan
- Structure and roof framingSite meeting 8 minutesDone Jul 10Planned Jun 26 · 2 weeks after plan
- Building closed inSite meeting 13 minutesDone Oct 9Planned Oct 2 · 7 days after plan
- Permanent heat onNorthstar schedule rev 4 (Oct 9)Forecast Nov 9Planned Nov 2 · 7 days after plan
- Gym floor installedSite meeting 14 (Oct 22)Forecast Nov 23Planned Nov 16 · 7 days after plan
- Substantial performanceNorthstar schedule rev 4 (Oct 9)Forecast Feb 19Planned Jan 29 · 3 weeks after plan
- Occupancy permitFollows substantial performance (+2 weeks)Forecast Mar 5Planned Feb 12 · 3 weeks after plan
How the finish date moved
- Contract schedule (Schedule B, Nov 18, 2025)Planned Jan 29
- Apr 2Moved to Feb 5 · Schedule rev 2: rock at the footings
- Jul 14Moved to Feb 12 · Schedule rev 3: steel delivery
- Oct 9Moved to Feb 19 · Schedule rev 4: RTU-2 and permanent heat