- Change OrderChange Order 1 · Reroute abandoned water line found at the new footingsHalden Architects · $18,600.001 versionCurrentHA-24-31_CO01.pdfRev 0Jan 17Signature lines:Halden Architects · Jan 17Riverside Community Association · Jan 22Northstar Construction · Jan 22
An old water line, not on the survey, ran through the new east footings.
- Change OrderChange Order 2 · Sound system rough-in for the gymnasiumHalden Architects · $9,850.001 versionCurrentHA-24-31_CO02.pdfRev 0Feb 21Signature lines:Halden Architects · Feb 21Riverside Community Association · Feb 26Northstar Construction · Feb 26
The association asked for conduit and boxes for a future sound system.
- Change OrderChange Order 3 · Rock excavation at the north footingsHalden Architects · $27,400.001 versionCurrentHA-24-31_CO03.pdfRev 0Mar 14Signature lines:Halden Architects · Mar 14Riverside Community Association · Mar 19Northstar Construction · Mar 19
Bedrock was higher than the geotechnical report expected.
- Change OrderChange Order 4 · Delete the exterior entrance canopy (credit)Halden Architects · -$12,400.001 versionCurrentHA-24-31_CO04.pdfRev 0Apr 25Signature lines:Halden Architects · Apr 25Riverside Community Association · Apr 30Northstar Construction · Apr 30
The association chose to defer the canopy to a later phase.
- Change OrderChange Order 5 · Reroute supply duct to clear the gym ceiling heightHalden Architects · $6,950.001 versionCurrentHA-24-31_CO05.pdfRev 0Jun 6Signature lines:Halden Architects · Jun 6Riverside Community Association · Jun 11Northstar Construction · Jun 11
Duct as drawn would have cut into the required gym clear height.
- Change OrderChange Order 6 · Additional exit signage requested by the fire inspectorHalden Architects · $4,200.001 versionCurrentHA-24-31_CO06.pdfRev 0Jul 18Signature lines:Halden Architects · Jul 18Riverside Community Association · Jul 23Northstar Construction · Jul 23
Two more illuminated exit signs, added at framing inspection.
- Change OrderChange Order 7 · Upgrade to a sprung gymnasium floorHalden Architects · $6,640.001 versionCurrentHA-24-31_CO07.pdfRev 0Sep 5Signature lines:Halden Architects · Sep 5Riverside Community Association · Sep 10Northstar Construction · Sep 10
Difference between the specified floor and a sprung system the association preferred.