Draw 6 is waiting on an updated cost-to-complete
Prairie Credit Union asked for a cost-to-complete before funding pay applicationpay application. The contractor's monthly bill for work done, checked by the architect before the owner pays. 9. The last one was in July. Without it the September payment can't be funded from the loan.
Next step: Northstar Construction: send an updated cost-to-complete; Riverside Community Association: forward it with the draw package